Through engineering and technical staff, Directorate of roads and bridges in Karbala implement a number of tasks for emergency maintenance of roads and bridges in the province to serve people and t

Through the engineering staff in Karbala, Roads...

Through the engineering staff in Karbala, Roads and bridges directorate completed Ahmed bin Al-Qasim road in the Al-Husseinieh in long of 3 km and at a cost exceeding 762 million dinars.

Engineer Essam Abbas, the general director of...

Engineer Essam Abbas, the general director of roads and bridges directorate, meets with delegation of the World Bank to discuss the implementation of the rehabilitation of Highway NO.1\VII and VIII

Through engineering and technical staff in...

, Through engineering and technical staff in karbala , Roads -and bridges directorate on oversees maintenance Fatima al alzahra road in length 2.75 kilometer of each corridor and in width of 10 met

In progress projects

Item Project Name Contractor Name Planned Execution Rate Actual Execution Rate Contract Commencement Date
1 Project of Expressway Ta’/6 Al-Bat’ha’ intersection bridge (left lane) Al-Mu’tasem Co. 100% 98% 10-05-02
2 Completing Al-Hafadh Bridge Ra’ad Khudhair Al-Ka’by Co. 100% 78% 13/09/2007
3 Rstoration of Marshlands Al-Chebayish City 127 km Noor Al-Hawra’ Co. 100% 17% 04-07-11
4 Marshlands Restoration Road of Al-Fuhood and Al-Hammar Bahjat Co. Thi Qar 15% 21% 06-08-13
5 And Al-Abrat Al-Shahlawiya Road at the Company’s cost) and Al-Mi’dan (Illegible Na’eem Al-Furat Co. 100% 40% 31/03/2013
6 Maqale’ Abu Ghar Road Kunooz Al-Ardh Co. 68% 45% 05-04-11
7 Nasiriya Akaika Road of 32.25 km length Kurama’ Al-Medina Contracting Co. 50% 46% 21/02/2013
8 Second Lane Nasriya – Samawa 41 km Ashoor Co. 100% 60% 01-04-11
9 Execution of Al-Bat’ha’ Intersection on the Expressway No. 1 (Ta’ / 6) Al-Bnayyan Contracting Co. 75% 40% 13/05/2012
10 Tel Shu’aib Road of 3 km length Al-Bahoor Contracting Co. 100% 60% 28/08/2011
11 Al-Batat Bridge in Suq Al-Shuyokh District Al-Mu’tasim Co. 68% 69% 16/07/2012
12 Construction of North Al-Nasiriya Bridge and ramps 1st stage River Bridge of Thi Qar Province Qenj Co. 15% 5% 17/04/2013
13 Rehabilitation of the complementary works for the construction of the road connecting the regulator No. 4 and Al-Hafadh Bridge in Thi Qar Province Al-Ghasaq Intl. Contracting Co. 55% 50% 15/04/2013
14 Kut-Nasiriya Weigh Station Sections Co. 98% 100% 22/09/2011
15 Nasiriya-Basra Weigh Station Sections Co. 73% 52% 13/12/2012
16 Nasiriya Samawa Weigh Station Sections Co. 95% 100% 19/10/2011
17 Al—Sudoor Bridge Al-Mu’tasim Co. 95% 96% 14/12/2010
18 2nd Lane Ba’qouba-Muqdadiya 40 km Ashoor Co. 94% 74% 01-03-11
19 Al-Sindiya Bridge Nebeeh Isma’eel 53% 8% 05-01-12
20 Qara-tepe – Omar Mendan Road Riyadh Al-Furatain 89% 89% 05-06-12
21 Road 18.5 km from Khalis-Udhaim Intersetion Khalaf Abdul-Kareem 100% 9% 12-01-02
22 Construction of intersection and bridge south of Al-Udhaim Dam Al-Sariya Co. 100% 80% 16/11/2002
23 2nd Lane Old Ba’qooba – Baghdad Road Beny Sa’ad part of 11.75 km length Al-Sar Contracting Co. 10% 32% 18/11/2012
24 Construction of the 2nd lane of Ba’qooba-Muqdadiya-Khanaqeen Road (Jelawla’ crossroad-Al-Sa’diya crossroad) of 5.5 km length Noor Al-Sana Co. 42% 47% 16/04/2013
25 Abu Saida Weigh Station Melath Al-Salam and Co., Nakheel Al-Sahl 100% 87% 14/06/2012
26 Himreen Weigh Station Melath Al-Salam and Co., Nakheel Al-Sahl 94% 58% 14/06/2012
27 Al-Kabashy Weigh Station Melath Al-Salam and Co., Nakheel Al-Sahl 100% 86% 14/06/2012
28 Al-Udhaim Weigh Station Melath Al-Salam and Co., Nakheel Al-Sahl 100% 63% 14/06/2012
29 Al-Mansooriya Weigh Station Melath Al-Salam and Co., Nakheel Al-Sahl 100% 89.50% 14/06/2012
30 Execution of the 2nd stage of Al-Gardhiya Brifg Nejran and Jennet Al-Khaleej Co. 100% 40% 29/01/2009
31 Al-Gardhiya Bridge Al-Noor Al-Thaqib and Al-Ghasaq Co. 100% 57% 21/10/2008
32 2nd legth of Al-Swaira entrance Hammoraby Co. 12% 12% 11-01-12
33 Rehabilitation of Kut – Jassan – Bedra Road Al-Qasrain Co. 100% 68% 20/10/2012
34 Rehabilitation of Al-Quda Village Road Bait Al-Asal Co. 100% 87% 24/11/2012
35 Rehabilitation of Al-Karama Bridge Ufq Al-Zawra’ and Barakat Meesan 85% 20% 25/01/2013
36 Construction of Kut-Bedra-Mahran Road, 1st stage, 40 km, including Kelal Bridge Hamoraby Bridge 10-02-13
37 Kut-Jassan Weigh Station Sections Co. 52% 69% 16/09/2011
38 Ta’ 6 Expressway Project, Section km (0-36) Section (117-145) Left Lane Hamooraby Co. 100% 92% 01-02-09
39 Ta’ 6 Expressway Bridges Project km (000+0)-(819+144)(Right Lane) Al-Mu’tasim Co. 98% 65% 10-11-11
40 Ta’ 6 Expressway Project Section km (000+0-000+47) (Right Lane) Hammoraby Co. 65% 51% 10-11-11
41 Remaining works of Diwaniya-Samawa Road Nabdh Al-Rafidain Co. 100% 100% 22/07/2010
42 Reconstruction of the upper bridge (53+975) Expressway Ashbal Al-Dhayaghim Co. 100% 75% 30/12/2012
43 Dora-Yousifiya Road Hammoraby Co. 17% 15% 01-11-12
44 Reconstruction of Al-Radhwaniya Bridge (15+500) Sada Baghdad Co. 100% 85% 28/09/2011
45 Reconstruction of Al-Adl intersection on Abu-Ghraib Expressway Ghadaq Al-Tabi’a Co. 100% 99% 07-07-11
46 Al-Qa’qa’ Bridge Al-Qabael Co. 100% 92% 05-08-12
47 Execution of Jdaidat Al-Shat Road of 4.6 km length in Diyala Thira’ Dijla Contracting Co. 100% 62% 29/02/2012
48 Construction of the 2nd Lane of Tarmiay Baghdad Entrance – Mosul Road of 13 km length Hammoraby Co. 100% 22% 20/09/2012
49 Completing Al-Za’ireen Service Road (Baghdad – Al-Sekka Bridge) of 21.75 km length Ashur Co. 12% 3% 07-03-13
50 Al-Wihda Subdistrict Weigh Station Melath Al-Salam Co. and Nakheel Al-Sahl Co. 100% 89% 14/06/2012
51 Al-Rashdiya Station Melath Al-Salam Co. and Nakheel Al-Sahl Co. 75% 8% 14/06/2012
52 Al-Haswa Customs Station Melath Al-Salam Co. and Nakheel Al-Sahl Co. 95% 80% 14/06/2012
53 Al-Nahrawan Weigh Station Melath Al-Salam Co. and Nakheel Al-Sahl Co. 100% 87% 14/06/2012
54 Al-Yousifiya Weigh Station Melath Al-Salam Co. and Nakheel Al-Sahl Co. 93% 49% 14/06/2012
55 Baghdad – Baqouba Old Road Station Melath Al-Salam Co. and Nakheel Al-Sahl Co. 81% 14% 14/06/2012
56 Al-Latifiya Weigh Station Melath Al-Salam Co. and Nakheel Al-Sahl Co. 91.10% 47% 14/06/2012
57 Al-Niba’iy Road Weigh Station Melath Al-Salam Co. and Nakheel Al-Sahl Co. 93.20% 33% 14/06/2012
58 Sab’ Al-Bor Weigh Station Melath Al-Salam Co. and Nakheel Al-Sahl Co. 86.54% 57% 14/06/2012
59 Al-Niba’iy Checkpoint Weigh Station Melath Al-Salam Co. and Nakheel Al-Sahl Co. 93.20% 33% 14/06/2012
60 Baghdad Checkpoint Weigh Station Malek Najy & Ardh Al-Rahma Co. 100% 5% 15/08/2012
61 Ta’ 6 Expressway Project (000+95-000+120) and earth filling works only for the Section km (000+120-000+120) (Right Lane) Hammoraby Co. 41% 23% 10-11-11
62 Ta’ 6 Expressway Project (000+130-819+144), mixed gravel, pavement and furnishing works for the Section km (000+120-000+130) (Right Lane) Ashur Co. 45% 21% 10-11-11
63 Ta’ 6 Expressway Project Section km (36+117) (Left Lane) Ashur Co. 100% 92% 01-02-09
64 Bridges of Al-Samawa Branch Road km (400+1-144+27) and main Road No. 8 at the entrance of Al-Samawa City Section km (039+0-740+3) (Right Lane) Al-Mu’tasim Co. 92% 34% 10-11-11
65 Al-Samawa Branch Road Right Lane Section km (400+1-144+27) and Al-Samawa North intersection development of the main Road No. 8 at the entrance of Al-Samawa City Section km (039+0-740+3) (Right Lane) Hammoraby Co. 57% 40% 10-11-11
66 Ta’ 6 Expressway Project Section (000+47-000+95) (Right Lane) Ashur Co. 52% 45% 10-11-11
67 Construction of Al-Swair Bridge and Ramps Khairat Al-Junoob and Al-Farazsaq Co. 100% 100% 07-01-08
68 Second Lane Samawa-Nasiriya 48.15 km Ashur Co. 47.80% 60% 29/08/2012
69 Al-Samawa Branch Road (Left Lane) Section (400+1-644+27) Ashur Co. 59% 46% 10-11-11
70 2nd Lane of Al-Samawa / Abdulla Abu Najim Salt Flat Road 18.2 km with 3 bridges Burj Al-Esar Co. 31% 26.90% 19/09/2012
71 Contract for the rehabilitation of the road leading to Amed Village (Al Jnaj) of 2.55 km length Burj Al-Hameediya Co. 06-04-13
72 Al-Ameriya Bridge of Al-Fallouja Al-Fao Co. 100% 99% 11-02-10
73 Al-Falluja 3rd Bridge Al-Mu’tasim Co. 70% 68% 15/09/2011
74 Haditha Bridge and Ramps Nabeeh Ismaeel 63% 20% 14/05/2012
75 Rawa –Al-Hadhar Road 1st Part 67 km Ajeel Thyab Al Khirbeet and Mohammed Shaker 50% 6% 05-06-12
76 Reconstruction of the upper bridge on the Expressway 56 km Husaiba Al-Sharqiya Co. 100% 50% 24/07/2011
77 Construction of Ramady-Haditha Road 2nd Lane of 20 km length Hammoraby Co. 56% 43% 23/10/2012
78 Construction of Jwaiba – Al-Hamdhiya (Al-Ma’moon) Bridge Hammoraby Co. 6% 6% 24/03/2013
79 Construction of Ramady-Haditha Road 2nd Lane of 20 km length Hammoraby Co. 8% 3% 07-11-13
80 Weigh Stations of Al-Saqlawiya Al-Meezan Intl. Co. 87% 85% 22/10/2012
81 Km35 Al-Ramady West Weigh Stations Al-Meezan Intl. Co. 87% 89% 22/10/2012
82 Km60 Al-Rutba West Weigh Stations Al-Meezan Intl. Co. 100% 85% 22/10/2012
83 Weigh Stations of Al-Habaniya Al-Meezan Intl. Co. 97% 87% 22/10/2012
84 Weigh Stations of Al-Qa’em Al-Meezan Intl. Co. 87% 80% 22/10/2012
85 Weigh Stations at Al-Waleed Border Point Al-Meezan Intl. Co. 87% 60% 22/10/2012
86 Weigh Stations at Traibeel Station Al-Meezan Intl. Co. 80% 87% 22/10/2012
87 Weigh Stations at Al-Karma Station Al-Meezan Intl. Co. 55% 28% 22/10/2012
88 2nd Lane Diwaniya-Deghara-Shawmaly Hammoraby Co. 38% 38% 30/08/2012
89 Diwaniya-Afak-Abdair (2nd Stage) 32 km Hammoraby Co. 14% 17% 24/11/2012
90 Diwaniya-Afak-Al-Bdair (1st Stage) 20 km Hammoraby Co. 24% 28% 30/10/2012
91 Afaq Weigh Station Ufq Al-Zawra Co. and Barakat Meesan Co. 99% 20% 31/10/2012
92 Al-Diwaniya Weigh Station Ufq Al-Zawra Co. and Barakat Meesan Co. 89.90% 18%` 31/10/2012
93 Al-Hafar Weigh Station Ufq Al-Zawra Co. and Barakat Meesan Co. 97%` 16% 31/10/2012
94 Al-Seniya Weigh Station Ufq Al-Zawra Co. and Barakat Meesan Co. 100% 0% 31/10/2012
95 Qal’at Saleh Bridge Hamed Rasheed & Co. 100% 97% 23/08/2005
96 Al-Dafas Bridge and Ramps north Al-Amara city Al-Bahr Al-Abyadh and Al-Ferazdaq 100% 76% 04-05-08
97 Ali Al-Gharby Bridge and Ramps Anwar Sura Co. 43% 40% 19/09/2012
98 Execution of concrete bridge at Al-Mejar Al-Kabeer District Al-Tatweer Co. 80% 33% 25/12/2012
99 Construction of Two Bridges and junction to process torrents and rains at Ali Al-Gharby Ashur Co. 35% 50% 22/07/2013
100 Ali Al-Gharby Weigh Station Sections Co. 98% 100% 08-07-11
101 Ghzaila Weigh Station Sections Co. 100% 100% 08-07-11
102 Execution of Eskandariya-Mussayab Al-Za’ereen Road Ashur Co. 70% 94% 20/07/2011
103 Al-Reghaila – Abu-Gharag Checkpoint Al-Za’ereen Road Ashur Co 41% 42% 20/07/2011
104 Execution of Hilla – Keesh Road Hammoraby Co. 47% 54% 12-08-09
105 Execution of Hilla – Abu-Gharag Al-Za’ereen Road Ashur Co 23% 22% 20/07/2011
106 Al-Kifl – Al-Qasim Road Jawharat Babel Co. 100% 90% 08-04-10
107 Development, Rehabilitation and Maintenance of Baghdad – Karbala Road from Al-Sikka Bridge to Al-Musayab Intersection 1st Part of 21 km length Straco of Lebanon 78% 38% 01-08-13
108 Al-Eskandarya – Maqam Al-Khudr Road Rawnaq Al-Mas Co. 16% 17% 04-07-13
109 Hashmiya – Mifhatiya Shawmaly Ardh Al-Hamad & Brooklyn 1.60% 1.60% 07-05-13
110 Al-Kifil Weigh Station Ufq Al-Zawra Co. and Barakat Meesan Co. 100% 54% 31/10/2012
111 Expressway Weigh Station Ufq Al-Zawra Co. and Barakat Meesan Co. 80% 30% 31/10/2012
112 Al-Shawmaly Weigh Station Ufq Al-Zawra Co. and Barakat Meesan Co. 100% 64% 31/10/2012
113 Al-Wind Weigh Station Ufq Al-Zawra Co. and Barakat Meesan Co. 88% 8% 31/10/2012
114 Al-Hindiya Bridge Ramps Ashur Co. 99% 78% 03-01-12
115 2nd Lane of Karbala – Razzaza / Al-Ukhaidhur Road of 45 km length JV of Kunooz Al-Ardh and Al-Tafadhul 79% 73% 02-07-11
116 Construction of Bridge Intersections of Al-Hindiya Bridge Ramps Al-Sado and Al-Khaleej Al-Kabeer Co. 100% 67% 24/02/2010
117 Execution of Karbala – Musayab Al-Za’ereen Road Ashur Co. 100% 97% 20/07/2011
118 Execution of Al-Za’ereen Road from Shattallah Bridge to Al-Ibrahimiya Checkpoint Ashur Co. 100% 99.50% 20/07/2011
119 Execution of Karbala – Najaf Al-Za’ereen Road Hammoraby Co. 100% 99% 20/07/2011
120 Development, Rehabilitation and Maintenance of Baghdad – Karbala Road from Al-Musayab – Jurf-AlSakhar Intersection to Karbala Entrance of 25 km length Huhub Co. of Malaysia 100% 18% 02-07-13
121 Construction of the 2nd Lane of Karbala-Razzaza-Al-Ukhaidhir 2nd Stage 45 km Ashur Co. 27/09/2013
122 Karbala Weigh Station Ufq Al-Zawra Co. and Barakat Meesan Co. 100% 51% 31/10/2012
123 Rehabilitation, Expansion and Maintenance of Karbala – Hindiya Road from Station (0+0) Al-Ibrahimiya to Station (500+9) A-Tafadhul Contracting Co. 39% 30% 02-05-13
124 Al-Azba – Al-Rhaima Bridge Al-Mu’tasim Co. 100% 38% 07-04-12
125 Al-Hijj Road 1st Stage / 50 km Khairat Al-Najaf Co. and Alwifaq Co. -- -- 07-02-13
126 Ghammas Weigh Station Khairat Al-Najaf Co. and Alwifaq Co. 99% 19% 31/10/2013
127 Al-Maqali’ Road Weigh Station Ufq Al-Zawra Co. and Barakat Meesan Co. 70% 8% 31/10/2013
128 Najaf-Karbala Weigh Station Ufq Al-Zawra Co. and Barakat Meesan Co. 100% 43% 31/10/2013
129 Kufa-Kidil-Babel (Abbasiyat) Weight Station Ufq Al-Zawra Co. and Barakat Meesan Co. 100% 1% 31/10/2013
130 Qafisiya-Shinafiya Weigh Station Ufq Al-Zawra Co. and Barakat Meesan Co. 88% 9% 31/10/2013
131 Remaining Works of 1st & 2nd Qoory Chai Bridges Hammoraby Co. 100% 100% 15/01/2012
132 2nd Lane of Baghdad-Kirkuk Road (Suleiman Bek Part) Salah Al-Din Daqoq 26,413 km Hammoraby Co. 99% 97% 08-04-10
133 2nd Lane of Baghdad-Kirkuk Road (Shenshal – Al-Udhaim Part) Salah Al-Din Daqoq 38,450 km Partnership Al-Dulaimy and Ranya Asphalt 100% 90% 19/07/2010
134 Construction of the 2nd Lane of Kirkuk-Dibis Road of 26.9 km length Jehan Contracting Co. 17% 23% 14/10/2012
135 North Gas Checkpoint Weigh Station Malek Najy & Ardh Al-Rahma Co. 100% 92% 15/08/2012
136 Taza – West Baghdad Checkpoint Weigh Station Malek Najy & Ardh Al-Rahma Co. 100% 90% 10-08-12
137 Keewan Weigh Station – near Keewan Checkpoint Malek Najy & Ardh Al-Rahma Co. 91% 82% 28/12/2012
138 Qara Salim Weigh Station – Alton Kopry Subdistrict Malek Najy & Ardh Al-Rahma Co. 100% 88% 15/10/2012
139 Tikrit Checkpoint Weigh Station Malek Najy & Ardh Al-Rahma Co. 79% 82% 12-06-12
140 Construction of Baiji Concrete Bridge and Ramps Al-Akabir Contracting Co. 100% 99% 25/11/2007
141 Construction of Zghaitoon and Al-Shay Bridges Ashbal Al- Dhayaghim Co. and Nabdh Al-Rafidain Co. 5% 10% 03-10-13
142 Construction North Tikrit Bridge and Ramps / 1 stage Al-Mu’tasim Co. 1% 1% 07-03-13
143 Al-Dijail Weigh Station Naseem Al-Khadra’ Co. and Al-Meezan Co. 92% 31% 22/10/2012
144 Samarra’ Weigh Station Naseem Al-Khadra’ Co. and Al-Meezan Co. 0 0 22/10/2013
145 Tikrit – Al-Alam Weigh station Naseem Al-Khadra’ Co. and Al-Meezan Co. 86% 30% 22/10/2013
146 Baiji Weigh Station Naseem Al-Khadra’ Co. and Al-Meezan Co. 91% 54% 22/10/2012
147 Reconstruction of Al-Fayha’ (formerly Khalid Ibn Al-Waleed Bridge) Industrial Design and Construction Co. 98% 73% 02-06-12
148 Marshlands Restoration / Al-Khait Al-Awal Road / Bait Nghaimis / Alghadir Hamasa Dhay Al-Rafidain Co. 82% 76% 29/05/2013
149 Marshlands Restoration / Al-Harooniya with Al-Dawoody Bridge Bareeq Al-Husam Co. 100% 100% 01-12-12
150 Reconstruction of Al-Qurna Concrete Bridge Al-u’lu’a Co. 47% 35% 21/05/2012
151 Rehabilitation and Development of Shat Al-Arab Atba Subdistrict of 69250 km Ufq Al-Zawra’ Co. 35% 12% 30/12/2012
152 Execution of the remaining works of Ez Al-Din Saleem Bridge Abdul-Jabbar Al-Hammad Co. 20% 11% 25/03/2013
153 Al-Shalamcha Weigh Station Sections Co. -- -- --
154 Basra – Amara Weigh Station Sections Co. 100% 100% 26/09/2011
155 Construction of Kesek Rabee’a Road / 1st Stage Al-Jubail Co. and Al-Bah Al-Abyadh Co. 100% 99% 05-08-08
156 Execution of Tel Afar – Tel Abta – Al-Hadhar Road Al-Nijood Co. 100% 17% 26/07/2006
157 Execution of Al-Mosul 6th Bridge Al-Mu’tasim 0% 0% 03-12-13
158 Kirkuk Checkpoint Weigh Station Malek Najy & Ardh Al-Rahma Co. 100% 59% 15/08/2012
159 Arbil Checkpoint Weigh Station Malek Najy & Ardh Al-Rahma Co. 100% zero 15/08/2012
160 Bawabat Al-Sham Vheckpoint Weigh Station Malek Najy & Ardh Al-Rahma Co. 100% 30% 15/08/2012
161 Duhok Checkpoint Weigh Station Malek Najy & Ardh Al-Rahma Co. 91% 39% 15/08/2012
162 Khor Seabad Checkpoint Weigh Station Malek Najy & Ardh Al-Rahma Co. 77% 55% 15/08/2012
163 Rabee’a Checkpoint Weigh Station Malek Najy & Ardh Al-Rahma Co. 100% 51% 15/08/2012
164 Al-Tahrir Checkpoint Weigh Station Malek Najy & Ardh Al-Rahma Co. 97% 52% 15/08/2012